Capital Works Project : News Student Amentities Timeline

images.png
Mattoni Constructions will be the building company.

Friday 11 April

- Demolition works begin on the current student facilities

Friday 11 April - Monday 28 April

- Demolition, removal and clean up of the site will take place

- Temporary Ablution Block for students will be erected

- Temporary relocation of students’ bubbler and water station

- Site blocked off for work to begin. Students will not be permitted in this area once tradespeople begin their work.

Tuesday 29 April onwards

- Building of new students amenities. Various trade groups will then be sequenced to come in and out to complete different sections of the work. Given the small area they will be working in, only one trade group will come in at one time.